SCOPE OF WORK: Excavation, cutting into the pipeline, purging the pipeline with air in order to clean out, capping the ends, backfilling, and labeling the pipeline for the AER for more than 300 pipeline abandonments.
CHALLENGES/UNIQUENESS: The work was completed within an area that lacked maps and historical information due to the land having had several owners throughout its existence. Also, at 300+ pipeline abandonments, the actual size of this project was unique – this was an exceptionally large scope for this type of work. Our Integrity project team completed this project on time and under budget.
TIME TO COMPLETE: 9 months