SCOPE OF WORK: 110km of various 4” -12” steel pipeline with 60kms of liner installation.
CHALLENGES/UNIQUENESS: Work performed during winter conditions with majority of ROW on muskeg. Applying proper coordination of a 200-man crew and 40 pieces of heavy equipment, the project was successfully completed on time.
TIME TO COMPLETE: 3.5 months